What did we expect to happen?

What was the plan, the goal and the standard we aimed for?

We planned to launch the new pricing page on Tuesday with all three plans and the FAQ live.
The goal for the conference booth was 150 qualified conversations over two days.
We expected the data migration to finish overnight with no customer-facing downtime.
What actually happened?

What really happened, step by step, from each person's view?

The pricing page went live on Thursday because legal review started two days late.
We had 96 qualified conversations, and most of them were on day one.
The migration overran by three hours and two enterprise customers noticed slow logins.
Why was there a difference?

What explains the gap between plan and reality, good or bad?

Legal review wasn't in the launch plan, so nobody booked time for it.
Day two was quieter because the keynote moved to the other end of the venue.
We tested the migration on a copy of the data that was a third of the real size.
What will we keep or change?

Which lessons learned will we carry into the next one?

Change: add legal review to the launch checklist with a fixed two-day slot.
Change: book a booth near the main hall, or give people a reason to walk over.
Change: rehearse migrations on full-size data, even if the rehearsal takes longer.

What is an after action review?

An after action review (AAR) is a short, structured debrief built on four questions: what did we expect to happen, what actually happened, why was there a difference, and what will we keep doing or change next time. The US Army made it standard practice, and hospitals, emergency services and businesses have used it since, because it suits any team that has just finished something and wants to learn from it while the details are fresh. It's lighter than a full post-mortem, and nothing has to have gone wrong. Here's how it runs in TeamRetro. Everyone adds their own observations privately first, so the most senior person in the room doesn't set the story before anyone else has written a word. Ideas are then grouped, discussed and voted on, which keeps the session on the gaps that matter instead of every detail of the day. The last question turns the discussion into lessons learned, and the actions you agree on get an owner and a due date, so they come up again at your next session. Use it after a launch, an event, a client pitch, a busy shift, a training exercise or a sprint that didn't go as planned. Keep it short: most teams finish in 30 to 45 minutes. Export the report when you're done, so the lessons stay findable for the next team in the same situation.

After action review format

What did we expect to happen?

What was the plan, the goal and the standard we aimed for?

Start with the plan, not the outcome. Ask what the goal was, what success looked like and what standard the team was working to. Keep it factual and save judgment for the later questions. If people remember the plan differently, capture each version: a plan that wasn't shared is often the first lesson of the session.

What actually happened?

What really happened, step by step, from each person's view?

Build a shared account of events before anyone explains them. Each person saw a different part of the work, so ask what they saw and when, not what they think caused it. Agree on the order of events if it matters. If blame starts creeping in, steer it to the next question.

Why was there a difference?

What explains the gap between plan and reality, good or bad?

This is where the learning sits. Look at gaps in both directions: when something went better than planned, ask why as well, so you can repeat it. Keep asking why until you reach a condition the team can change, such as a missing step, an untested assumption or an unclear owner, rather than a person to blame. Use voting to pick the two or three gaps worth the most discussion.

What will we keep or change?

Which lessons learned will we carry into the next one?

Turn each gap into a lesson someone outside the room could use: a step to add, a check to run, a habit to keep. Separate what the team can change itself from what needs someone else's help. Then agree on a small number of actions, each with an owner and a due date recorded in TeamRetro, so they come up at your next session. Two or three owned actions beat a long list nobody follows up on.

When to use this retrospective

  • A launch, event, campaign or pitch has just finished and you want to compare the plan with what happened while it's still fresh
  • Something went better than expected and you want to know why, so you can repeat it on purpose
  • A shift, exercise or busy period didn't go as planned and you need a short, blameless debrief, not a full investigation
  • Your team runs the same kind of work often, such as releases, onboarding or client deliveries, and you want each one to teach the next
  • You want a debrief that fits in 30 to 45 minutes instead of a half-day post-mortem

Suggested icebreaker questions

  • In one word, how did it go compared with what you expected?
  • What is one moment from this piece of work you'll remember?

Want a warm-up your team plays, not just answers out loud? Browse free icebreakers →

Ideas and tips for your retrospective meeting

  • Run it within a day or two. An after action review works because it captures detail before people forget it or retell it
  • Say the ground rule out loud: you're reviewing the plan and the work, not grading people. Ask the most senior person to speak last
  • Give the first question real time. If the team can't agree on what was supposed to happen, that's a finding in itself
  • Look at what went better than planned as well as what went worse. A win you can't explain is hard to repeat
  • Keep reviews short and regular. Several small reviews after routine work teach more than one big review a year
  • Open each review by checking the last one's actions. Knowing they'll be checked is what gets them done

Frequently asked questions

What is an after action review?
It's a short, structured debrief your team runs after a piece of work, built around four questions: what did we expect to happen, what actually happened, why was there a difference, and what will we keep or change. It started in the military and is now common in healthcare, emergency services and business. The output is a set of lessons learned and a few owned actions.
What are the four questions of an after action review?
What did we expect to happen? What actually happened? Why was there a difference? What will we keep or change? This template gives each question its own column, in that order.
How is an after action review different from a post-mortem?
An after action review is shorter and lighter, and it suits any piece of work, including work that went well. A post-mortem usually follows a failure or the end of a large project, and it goes deeper into root causes and timelines. If something went seriously wrong, use the Project Post Mortem Template instead.
How long does an after action review take?
Most teams finish in 30 to 45 minutes. A quick review straight after routine work can take 15 minutes, and a large event or exercise may need an hour.
Who should take part in an after action review?
Everyone who did the work, including people who only touched part of it. Keep the group small enough for honest conversation. Leaders take part as equals and speak last, so the review reflects what happened rather than the most senior view.
How do you capture lessons learned from an after action review?
The final question produces them. Write each lesson so someone outside the room could act on it, turn the most important ones into actions with an owner and a due date, and export the report so the next team can find it.